Full electrical installation and commissioning of a state-of-the-art construction waste recycling plant featuring 80+ metres of conveyors, shakers, and blowers powered by a 400kVA generator system.

Construction waste recycling plant electrical installation by CPR Electrical for Eco Resources in Perth WA

Overview

CPR Electrical delivered the complete electrical installation and commissioning of a purpose-built recycling plant for Eco Resources, designed to process general construction waste by separating metal and lightweight materials for hand sorting. The plant spans over 80 metres in length with a running load of approximately 400 amps, powered by a 400kVA generator with a sequential start mechanism to manage current draw during startup.

CPR managed the entire installation scope including SWA cables on cable trays and plant structures, coordinating with Metroid Electrical Engineers (a national partner of Skala) who supplied and commissioned the Motor Control Centre (MCC).

Scope of Work

• Installation and commissioning of complete recycling plant

• Multiple conveyors, shakers, and blowers installation

• SWA cables on cable trays and plant structures

• 400kVA generator integration with sequential start system

• Coordination with Metroid/Skala for MCC commissioning

• Ongoing service and maintenance

400kVA generator integration for Eco Resources construction waste recycling plant by CPR Electrical
Electrical installation across 80-metre recycling plant for Eco Resources Perth WA
Completed recycling plant electrical commissioning by CPR Electrical for Eco Resources Perth

Challenges & Solutions

Challenge

Coordinating the electrical installation of an 80-metre recycling plant alongside concurrent civil and mechanical construction activities required precise staging and sequencing to avoid trade conflicts and delays. The generator-powered system — running approximately 400 amps through a 400kVA generator — demanded careful load management through sequential start design to prevent overload during startup, requiring the electrical design to account for inrush currents across multiple conveyors, shakers and blowers starting in sequence.

Solution

CPR synchronised installation works with Skala's construction schedule, completing electrical fit-out in each section as it was built to minimise overall project duration. The sequential start system was engineered and tested to ensure reliable startup under full load conditions, with SWA cables installed on cable trays and plant structures throughout the 80-metre facility. Coordination with Metroid Electrical Engineers for MCC commissioning was managed seamlessly, delivering the project with zero variations, zero incidents and zero near misses.

Project Outcome

Delivered on time with zero variations, zero incidents, and zero near misses. Extensive pre-commissioning testing ensured flawless operation from day one. CPR now provides ongoing service and maintenance for the plant.

Key Project Details

Client: Eco Resources

Location: Perth, WA

Industry: Waste & Recycling

Project Type: Industrial Plant Installation

Duration: Multi-phase project

Get a Quote or Book a Service

Contact us today to discuss your electrical project, maintenance program, or complex project works, servicing Perth, Bunbury, and all of Western Australia.

Fully Licensed & Insured

24/7 Emergency Support

Industrial & Remote Site Ready

LVR/CPR Trained & Certified

20+ Years Experience

AS45001:2018 Accredited

Perth

Bunbury

South West

Pilbara

Goldfields

Regional WA

bottom of page